Asphaltic Concrete Enterprise Limited
Client – National Works Agency
Completed in 2017
Mona Road Rehabilitation Works commenced in May 2017 and was completed in December 2017. The Mona Road has been plagued with frequent flooding from even minimal rainfall forcing many motorists to find alternate routes during these times. As part of the rehabilitation efforts, culverts were installed and connected to a large box culvert to take away water from the roadway more efficiently. Widening of a section of the corridor and construction of sidewalks were carried out to ease traffic congestion and allow for ease of access for pedestrians, respectively.
The improvement works includes;
- Manholes
- HDPE Culverts
- Box Culvert
- Construction of boundary walls
- Sidewalks,
- Kerb walls,
- Base and Sub-Base
- Prime
- Asphaltic concrete pavement.